71/91 Interchange Project

Client

Riverside County Transportation Commission

Challenge
Solution
  • Detailed Schedule Analysis
    Performed in‑depth peer review of the contractor’s Primavera P6 schedules, validating logic, sequencing, and completion feasibility.
  • Critical Path Evaluation
    Identified the true drivers of project completion and analyzed shifts between baseline and final as‑built schedules.
  • Delay Impact Assessment
    Quantified schedule impacts related to differing site conditions, environmental work restrictions, and railroad moratoriums.
  • Claim Support
    Evaluated the contractor’s $5.9M delay claim through targeted variance analysis and forensic schedule review.
  • Risk Visibility
    Provided real‑time insight into completion risk to support owner decision‑making during project closeout.
Results
  • Successful Project Delivery
    Provided schedule and claims analysis that supported timely project closeout and informed owner decision‑making.
  • Defensible Claim Resolution
    Delivered clear, objective findings that strengthened the owner’s position during delay claim negotiations.
  • Improved Schedule Transparency
    Identified the true drivers of completion, giving the owner clear visibility into project risk and responsibility.
  • Reduced Claims Exposure
    Helped minimize potential financial and contractual risk through independent, technically sound analysis.