Case Study

Strata Solar Projects - Takt Planning using Primavera

Client

Strata Clean Energy

Executive Summary
The Challenge
As Strata Clean Energy continued advancing utility-scale renewable energy projects, it faced a familiar challenge seen across growing EPC and infrastructure organizations: project controls processes had to evolve faster than the systems and operating model supporting them.

Key challenges included:

  • Fragmented workflows across engineering, procurement, construction, and commissioning functions
  • Inconsistent schedule ownership and progress measurement expectations
  • Heavy reliance on external expertise during a critical transition period
  • A need to mature the Oracle Primavera P6 EPPM environment for long-term internal ownership
  • Manual and inconsistent reporting processes that limited efficient portfolio visibility
  • A need to better align operational planning data with Strata’s evolving reporting model

Strata needed more than just tactical scheduling support. It needed a partner who could help stabilize operations, improve governance, support technical platform maturity, and help build internal readiness for the next phase of growth.

CMC's Approach
Results
CMC helped Strata Clean Energy strengthen both its immediate project controls operations and its long-term internal readiness.

Outcomes included:

  • Successful buildout of Strata’s internal project controls and platform ownership capability
  • Upgraded and more mature Oracle Primavera P6 EPPM operating environment
  • Reduced manual reporting effort through better data and process alignment
  • Improved consistency in monthly reporting routines and executive-facing information flows
  • Clearer ownership of schedule updates, reporting responsibilities, and progress measurement
  • Improved readiness for internal IT and scheduler teams to manage the platform and processes
  • Better alignment across engineering, procurement, construction, and commissioning stakeholders
  • Stronger foundation for scalable reporting through Microsoft Power BI and Strata’s internal data environment

Why It Matters

For growing renewable energy developers, project controls maturity is not just about having schedules in place. It is about building a system of execution that connects planning, governance, reporting, and internal ownership.

CMC’s work with Strata Clean Energy demonstrates how the right project controls partner can help an organization:

  • Stabilize operations during transition
  • Strengthen enterprise governance
  • Improve confidence in reporting
  • Reduce reliance on external resources over time
  • Build a scalable foundation for future growth
More Case Studies
Strata Solar Project

Strata Solar Project

71/91 Interchange Project

71/91 Interchange Project

Disney Pirates of the Caribbean rebuild
Disney’s Pirates of the Caribbean

Disney’s Pirates of the Caribbean

Los Coches substation rebuild
Los Coches Substation Rebuild

Los Coches Substation Rebuild

Worker on wind turbine
TRTP 4-11 Project

TRTP 4-11 Project