Case Study

71/91 Interchange Project

Client

Riverside County Transportation Commission

Challenge
Solution
  • Detailed Schedule Analysis
    Performed in‑depth peer review of the contractor’s Primavera P6 schedules, validating logic, sequencing, and completion feasibility.
  • Critical Path Evaluation
    Identified the true drivers of project completion and analyzed shifts between baseline and final as‑built schedules.
  • Delay Impact Assessment
    Quantified schedule impacts related to differing site conditions, environmental work restrictions, and railroad moratoriums.
  • Claim Support
    Evaluated the contractor’s $5.9M delay claim through targeted variance analysis and forensic schedule review.
  • Risk Visibility
    Provided real‑time insight into completion risk to support owner decision‑making during project closeout.
Results
  • Successful Project Delivery
    Provided schedule and claims analysis that supported timely project closeout and informed owner decision‑making.
  • Defensible Claim Resolution
    Delivered clear, objective findings that strengthened the owner’s position during delay claim negotiations.
  • Improved Schedule Transparency
    Identified the true drivers of completion, giving the owner clear visibility into project risk and responsibility.
  • Reduced Claims Exposure
    Helped minimize potential financial and contractual risk through independent, technically sound analysis.
More Case Studies
Strata Solar Project

Strata Solar Project

71/91 Interchange Project

71/91 Interchange Project

Disney Pirates of the Caribbean rebuild
Disney’s Pirates of the Caribbean

Disney’s Pirates of the Caribbean

Los Coches substation rebuild
Los Coches Substation Rebuild

Los Coches Substation Rebuild

Worker on wind turbine
TRTP 4-11 Project

TRTP 4-11 Project